MV E-House 36kV for Artemisa development area

Artemisa (Cuba)

Country

Cuba

Year

2020

Description

Designed, construction and supply of n. 2 modular, pre-assembled and fully tested STC-Box cabins, for the expansion of a power plant serving the industrial area of Artemisa, in Cuba.

The plug & play solution, intended as the supply of a complete and ready-to-use system, guarantees high efficiency and, at the same time, quick installation. Each STC-Box compact substation is equipped with:

  • Medium-voltage (MV), gas-insulated (GIS) ATR-Ring switchgear (15 cells) 36kV 630A 16kA
  • Transformers
  • Inverter
  • Euro-SDS and Euro-P&C low-voltage panels (LV)
  • SCADA system for the control, supervision and automation of the plant
  • Lighting and air-conditioning systems
  • Auxiliary equipment

The compact substations, in consideration of the climatic and environmental conditions of the place of destination, are made of material resistant to humidity and salinity. Listening to the customer's needs means providing a quality solution, functional to its final application and destined to last over time.

Related projects to eHouse

N. 4 MV E-Houses 23kV for electrification of rural areas

Gonaives e Cabo Haitiano (Haiti)

The project has included n. 4 compact substations, with the aim to supply the electricity in the rural areas of Gonaives and Cabo Haitiano.

MV E-House 36kV for electrical grid

Tripoli (Libya)

The project has included the design and construction of n. 3 compact STC-Box substations, aiming to increase electrification in Libya.