Electrical installation works for industrial plant
Pieve Vergonte (Italy)
Country
Year
Description
The project has included the works to expand the high-voltage (HV) electrical substation serving the Hydrochem Srl plant in Pieve Vergonte (Piedmont).
C.R. Technology Systems has supervised and coordinated the team and the activities on site, carried out in record times.
In detail, HV electrical equipment was installed and put into service through a process of energizing the substation in two phases, and it included:
- Transformers
- Disconnectors
- Circuit-breakers
- Line insulators
- Surge arresters
- Portal 2 intermediate
- Portal 2 Side stalls A and B
Related projects to Electrical substation
HV/MV Substation 110/20kV 25MVA
Durrës (Albania)
Design, construction, installation and commissioning of electrical equipment for the high-voltage to medium-voltage substation HV/MV, connected to a hydro power plant.
N.2 HV/MV Substations 110/7.3kV 8MVA
Çemericë, Korçë (Albania)
The project has seen the implementation of 2 high-voltage to medium-voltage electrical substations in Çemericë and Korçë.