Electrical installation works for industrial plant
Pieve Vergonte (Italy)
Country
Year
Description
The project has included the works to expand the high-voltage (HV) electrical substation serving the Hydrochem Srl plant in Pieve Vergonte (Piedmont).
C.R. Technology Systems has supervised and coordinated the team and the activities on site, carried out in record times.
In detail, HV electrical equipment was installed and put into service through a process of energizing the substation in two phases, and it included:
- Transformers
- Disconnectors
- Circuit-breakers
- Line insulators
- Surge arresters
- Portal 2 intermediate
- Portal 2 Side stalls A and B
Related projects to Electrical substation
HV/MV Substation 110/34.5kV 2x40MVA
Artemisa (Cuba)
The project has included the study, construction, and installation of a hybrid GIS electrical substation, to supply energy to an industrial area in Atemisa.
Reactors and Medium-Voltage (MV) Switchgears for electrical substations
Jardines del Rey (Cuba)
Supply of materials and auxiliary accessories for the set-up of four reactors for the delivery of electricity in theJardines del Rey area in the province of Ciego de Ávila, in Cuba.