MV E-House 36kV for electrical grid

Tripoli (Libya)

Country

Libya

Year

2017

Description

The project has included the design and construction of n. 3 compact STC-Box substations, aiming to increase electrification in Libya.

Three compact modular substations, two of which with a power of 36kV 1250A 25kA and the other 4.16kV 1250A 25kA, consisting of:

  • Nr. 5 medium-voltage Normal Clad switchgear columns 36kV
  • Nr. 3 medium-voltage metal-enclosed ATR switchgear columns 4,16kV
  • Nr. 1 low-voltage (LV) Euro-SDS switchgear
  • Nr. 1 low-voltage(LV) Euro-480V switchgear
  • Spare parts

Related projects to eHouse

N.2 MV E-House 33kV 50MVA for Tesla Battery Energy Storage System

Yorkshire (United Kingdom)

Design, construction and supply of n. 2 switching stations equipped with power transformers, MV air-insulated ATR switchgear 36kV 1250A 20kA (1s), LV switchboards, and a SCADA system for the remote control, destined to Tesla BESS (Battery Energy Storage System).

MV E-House 4.16kV for oil plant

Nafoora (Lybia)

The project includes the design, construction, and commissioning of a compact and modular substation STC-Box and it is addressed to an oil plant in Nafoora, Sirte Bay, in Lybia.