N. 61 Transformation cabins for the electrical grid
Havana (Cuba)
Country
Year
Description
The ambitious realization has the aim of increasing the electric grid in the Cuban capital.
The project has involved the carrying out and start-up of the following transformation centers with radial conjugation:
- Nr. 3 STC-Kiosk 24 13.8kV 100kVA nominal voltages on low-voltage side 220V
- Nr. 10 STC-Kiosk 24 13.8kV 150kVA nominal voltages on low-voltage side 480V
- Nr. 5 STC-Kiosk 36 34.5kV 150kVA nominal voltage on low-voltage side 480V
- Nr. 1 STC-Kiosk 24 13.8kV 500kVA nominal voltages on low-voltage side 220V
- Nr. 1 STC-Kiosk 24 13.8kV 500kVA nominal voltages on low-voltage side 415V
- Nr. 2 STC-Kiosk 24 13.8kV 400kVA nominal voltages on low-voltage side 220V
- Nr. 3 STC-Kiosk 24 13.8kV 400kVA nominal voltages on low-voltage side 480V
- Nr. 11 STC-Kiosk 36 13.8kV 500kVA nominal voltages on low-voltage side 220V
- Nr. 1 STC-Kiosk 36 34.5kV 750kVA nominal voltages on low-voltage side 415V
- Nr. 3 STC-Kiosk 36 34.5kV 1500kVA nominal voltages on low-voltage side 415V
Related projects to Transformation cabin
N. 4 Transformation cabins for photovoltaic systems 3.15MW
Pontinia and Montalto (Italy)
Design, construction and commissioning of plug-in compact substations STC-Kiosk for 3.15MW photovoltaic systems in Pontinia and Montalto (Latina).
MV Transformation cabin 30kV for electrical grid
Halat (Lebanon)
The project, designed to increase the electricity grid of the Lebanese coast, has been installed in Halat, a municipality located in Jbeil District.