STC-Skid transformation cabins 4,8MVA

Padua (Italy)

Country

Italy

Year

2023

Description

Design, manufacturing and commissioning of plug-in Skid transformation cabins destined for a photovoltaic plant in the beautiful location of Monselice (Padua).

In detail, the project includes n. 2 Skid cabins 4,8MVA, equipped with MV switchgear ATR-Ring 24kV 630A 16kA, MV/LV oil-transformer, LV/LV auxiliary transformer, low-voltage switchboard Euro PC, UPS panels, AUX panels.