E-Houses for thermoelectric power plant

Chieti (Italy)

Country

Italy

Year

2024

Description

Design, construction and supply of n. 2 plug-in cabins for the Thermoelectric Power Plant in Chieti, Italy.

  • N. 1 e-House equipped with MV electrical switchgear 7.2kV 1250A 40kA(1s), n. 2 power transformers 350kVA, LV connection cables, air conditioning system, auxiliary equipment.
  • N. 1 e-House equipped with LV Power center panel, UPS, certified fiscal meters with GSM communication, air conditioning system, auxiliary equipment and provision for control station.
The project is destined to Gissi Thermoelectric Power Center, in Chieti. This plant works with a combined cycle to produce electricity, using only natural gas, with a power of approximately 840MW.
The system allows to optimize the use of fuel and to minimize the environmental impact, recovering the residual heat of the exhaust gases to produce additional energy.

Related projects to Power station

eHouse 33kV for BESS in Lancashire

Chorley (United Kingdom)

Design, construction and delivery of an eHouse destined to the BESS systems connected to a photovoltaic plant in Chorley, Lancashire (UK), with the aim of powering the local grid.

eHouse 33kV for BESS 50MW in Scotland

Pitkevy (Scotland)

E-House equipment for Battery Energy Storage System (BESS) 50MW in Pitkevy, Scotland.